🟠 Main Squeeze: The Sentinel Grove data center is back, smaller on paper and far more expensive
By Ja'Min Devon
Friday, November 20, 2026
Posted in:

What’s going on: The developers behind Sentinel Grove Technology Park, the data center proposed on Orange Avenue west of Fort Pierce, submitted revised plans to St. Lucie County on Oct. 21. The new version cuts the buildings down to 5 million square feet but raises the price tag to $36 billion, up from the $13.2 billion we reported when Planning and Zoning voted 4 to 2 to recommend denial last October. The County Commission still has not voted on it.
By the numbers:
- 1,218 acres, the same site off Orange Avenue west of Fort Pierce
- 5 million square feet of buildings, down from up to 15 million, though still larger than the 4.4 million square foot data center approved in Fort Meade
- $36 billion in total investment, which the developers tie to rising computer chip costs
- About 370 permanent workers earning an average of $150,600 a year including benefits
- Up to 1 gigawatt of electricity demand
- $248 million a year in property taxes to the county and its districts, up from $114 million in the first plan
- $123 million a year for St. Lucie Public Schools, up from $63 million
All of the tax and jobs figures are the developers’ own estimates.
What changed: The data center buildings would sit on about 600 acres at the northern end of the property, close to transmission lines and an FPL substation, and the rest of the land would stay in agriculture or open space. The developers say whichever big tech company operates the facility would have to put up more than $500 million in financial guarantees before FPL begins any work to serve it. A state law passed this year also requires data centers of this size to pay the full cost of their electricity.
The timing: The bigger tax projections arrived just as Florida voters approved Amendment 3, which opens the door to eliminating homestead property taxes. A project promising hundreds of millions of dollars a year lands differently in that environment.
Who owns the land: The property belongs to Epic Estates 68 LLC, which bought it for $15 million in July 2024. Shareholder documents list five investors:
- Sai Konda, who paid $3 million for 20%
- Reddisekhara Singala, who paid $2.7 million for 18%
- Vikram Pasham, who paid $1.875 million for 12.5%
- Venkateswara Bondalapati and Praveena Beeram, who together paid $7.425 million for 49.5%
Questions still open: Turning a $15 million land purchase into a $36 billion project raises an obvious one, which is where the money comes from. It’s also still unclear which tech company would actually run the facility, since the developers said they had no tenant lined up when they first presented it. Neighbors and ranchers were not shy the first time around, and when the county collected 28 online comments on the project, 27 were opposed.
What’s next: The County Commission has not scheduled a vote that I’ve seen. Back in December, county officials told us they wanted to tour data centers in other states and were studying Loudoun County, Virginia, and when a social media video made people think a vote was coming, the county confirmed it was not on the agenda. When a hearing date is set, I’ll let you know here and on social.